2024 No. 1151
Infrastructure Planning
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2024
Made 11th November 2024
Coming into force  12th November 2024

An application has been made to the Secretary of State under paragraph 2 of Schedule 6 to the Planning Act 2008, in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (“the 2011 Regulations”) for a non-material change to the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (“the 2015 Order”).
The Secretary of State, having considered the application and the responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the 2011 Regulations, has decided to make this Order amending the 2015 Order.

Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order.
Citation and commencement
1 
This Order may be cited as the Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2024 and comes into force on 12thNovember 2024.
Amendment to the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015
2 
The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 is amended in accordance with this Order.
Amendment to Part 3 (requirements) of Schedule 1 (authorised project)
3 
In Part 3 (requirements) of Schedule 1 (authorised project), in paragraph 5(8)(b) for “1,900 kilojoules” substitute “3,000 kilojoules”.
Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning Delivery
Department for Energy Security and Net Zero
11th November 2024