2023 No. 660
Infrastructure Planning
The Little Crow Solar Park (Amendment) Order 2023
Made 14th June 2023
Coming into force 15th June 2023

An application has been made under paragraph 2 of Schedule 6 to the Planning Act 2008 (the “2008 Act”) to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (the “2011 Regulations”) for a non-material change to the Little Crow Solar Park Order 2022 (the “2022 Order”).
The Secretary of State, having considered the application and responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the 2011 Regulations, has decided to make this Order amending the 2022 Order.

Accordingly, the Secretary of State, in exercise of the powers in paragraph 2 of Schedule 6 to the 2008 Act, makes the following Order—
Citation and commencement
1 
This Order may be cited as the Little Crow Solar Park (Amendment) Order 2023 and comes into force on 15th June 2023.
Amendment to The Little Crow Solar Park Order 2022
2 
The Little Crow Solar Park Order 2022 is amended by this Order as follows.
Amendment to Schedule 2, Part 1
3 
In Part 1 of Schedule 2—
(a) in paragraph 3(1) for the words “35th anniversary” substitute “45th anniversary”;
(b) in paragraph 4(1) for the words “35th anniversary” substitute “45th anniversary”.
Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning Delivery
Department for Energy Security and Net Zero
14th June 2023