2019 No. 446
Offshore Installations
The Offshore Installations (Safety Zones) Order 2019
Made 5th March 2019
Coming into force in accordance with article 1(2)
The Secretary of State makes this Order—
(a) in exercise of the powers conferred by section 22 of the Petroleum Act 1987 ; and
(b) for the purpose of giving effect to proposals submitted to her by the Health and Safety Executive under section 24(2A)  of that Act.
Citation and commencement
1 

(1) This Order may be cited as the Offshore Installations (Safety Zones) Order 2019.
(2) This Order comes into force on 6th March 2019 except for article 2(2) which comes into force as provided in article 2(3).
Establishment of safety zones
2 

(1) A safety zone is established around each installation specified in column 1 of Part 1 of the Schedule (being an installation stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984  specified in columns 2 and 3 of Part 1 of the Schedule.
(2) A safety zone is established around each installation specified in column 1 of Part 2 of the Schedule (being an installation to be stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of Part 2 of the Schedule.
(3) Paragraph (2) comes into force, as respects each installation—
(a) on 6th March 2019, where the installation arrives at its station before that date; and
(b) when the installation arrives at its station, in any other case.
Signed by the authority of the Secretary of State for work and pensions
Sarah Newton
Minister of State
Department for Work and Pensions

SCHEDULE
INSTALLATIONS
Article 2
PART 1 Installations stationed at the time the Order is made
(1) Name or other designation (2) Latitude (3) Longitude
Tyne, Block 44/18a, Tyne Field 54°26.913'N 02°28.779'E
Guinevere, Block 48/17b, Guinevere Field 53°24.850'N 01°16.337'E
PART 2 Installations not stationed at the time this Order is made
(1) Name or other designation (2) Latitude (3) Longitude
Alligin Well AP01, Block 204/20a, Alligin Field 60°22.333'N 04°11.631'W
Cook water injection well, Block 21/20a, Cook Field 57°21.54'N 00°49.98'E
DC6 Manifold Structure, Block 211/13a, Penguins Field 61°37.77'N 01°29.59'E
DC7 Manifold Structure, Block 211/13a, Penguins Field 61°36.72'N 01°32.66'E
DC8 Manifold Structure, Block 211/13a, Penguins Field 61°38.98'N 01°29.32'E
DC9 Manifold Structure, Block 211/8, Penguins Field 61°40.28'N 01° 29.02'E
Brodgar (H4) Subsea, Block 21/3a, Brodgar Field 57°55.373'N 0°27.216'E