2011 No. 663
Offshore Installations
The Offshore Installations (Safety Zones) Order 2011
Made 2nd March 2011
Coming into force 28th March 2011
The Secretary of State makes this Order —
(a) in exercise of the powers conferred by sections 22(1) and (2) of the Petroleum Act 1987 (“the Act”); and
(b) for the purpose of giving effect to proposals submitted to him by the Health and Safety Executive under section 24(2A) of the Act.
Citation and commencement
1 
This Order may be cited as the Offshore Installations (Safety Zones) Order 2011 and comes into force on 28th March 2011.
Establishment of safety zone
2 
A safety zone is established around each installation specified in column 1 of the Schedule (being installations stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the Schedule.
Signed by authority of the Secretary of State for Work and Pensions
Chris Grayling,
Minister of State
Department for Work and Pensions
2nd March 2011
SCHEDULE
SAFETY ZONE
Article 2


(1)Name or other designation of the offshore installation (2)Latitude North (3)Longitude
Kinnoull TowheadBlock 16/23, Andrew Field 58°14.23’ 01°34.21’ East
Clair RidgeBlock 206/8, Clair Field 60°44.18’ 02°29.65’ West
Falcon Well P1Block 210/25, Falcon Field 61°19.80’ 00°59.36’ East