The Secretary of State, in exercise of the powers conferred on him by section 22(1) and (2) of the Petroleum Act 1987 (hereinafter referred to as “the Act”) and of all other powers enabling him in that behalf, and for the purpose of giving effect to proposals submitted to him by the Health and Safety Commission under section 24(2A) of the Act, hereby makes the following order:
Citation and commencement
1 
This order may be cited as the Offshore Installations (Safety Zones) (No. 3) Order 2004 and shall come into force on 21st July 2004.
Establishment of safety zones
2 
A safety zone is hereby established around each installation specified in column 1 of the Schedule hereto (being an installation stationed in waters to which subsection (7) of section 21 of the Act applies) having a radius of five hundred metres from the point as respects that installation which has the co-ordinates of latitude and longitude according to European Datum (1950) specified in columns 2 and 3 of the Schedule.
Amendment of the Offshore Installations (Safety Zones) (No. 2) Order 2004
3 
In the Schedule to the Offshore Installations (Safety Zones) (No. 2) Order 2004, for “57° 29.42'” in column 2 there shall be substituted “59° 29.42'”.
Jane Kennedy
Minister of State,
Department for Work and Pensions
30th June 2004
SCHEDULE
SAFETY ZONES
Article 2


(1) (2) (3)
Name or other designation of the offshore installation Latitude North Longitude East
Nevis Central Lewis, Block 9/13a, Beryl Field 59° 33.35' 01° 24.06'
Arthur Production Well 1 and Subsea Manifold, Block53/02, Thames and Welland Field 52° 54.63' 02° 14.93'
Arthur Production Well 2, Block 53/02, Thames andWelland Field 52° 53.81' 02° 17.25'