1 
This Order may be cited as the Rivenhall Generating Station Extension (Correction) Order 2025 and comes into force on 9th April 2025.
2 
In relation to each of the provisions of the Rivenhall Generating Station Extension Order 2024 specified in the first column of the table in the Schedule, the erroneous text identified in the second column of each row is corrected in accordance with instructions in the third column.
Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning
Department for Energy Security and Net Zero
8th April 2025
SCHEDULE
Article 2
1 
Corrections to article 2(1)

Provision Erroneous text Correction
Article 2(1) definition of “the 2006 Act” “the 2006 Act” means the Companies Act 2006; Omit
Article 2(1) definition of “holding company” “holding company” shall have the meaning given in the 2006 Act; Omit
Article 2(1) definition of “subsidiary” “subsidiary” shall have the meaning given in the 2006 Act; Omit