1 

(1) This Order may be cited as the Offshore Installations (Safety Zones) (No. 2) Order 2025.
(2) This Order comes into force 21 days after the day on which it is made.
2 
A safety zone is established around each installation specified in column 1 of the table in the Schedule (being an installation stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the table in the Schedule.
3 

(1) The Offshore Installations (Safety Zones) (No. 2) Order 2007 is amended as follows.
(2) In the Schedule, omit the entry relating to “Chestnut Field Well 22/2A-12, Block 22/2A, Chestnut Field”.
4 

(1) The Offshore Installations (Safety Zones) (No. 3) Order 2007 is amended as follows.
(2 ) In the Schedule, omit the entry relating to “Well 22-11x, Block 22/2A, Chestnut Field”.
5 

(1 ) The Offshore Installations (Safety Zones) (No. 2) Order 2008 is amended as follows.
(2) In the Schedule, omit the entry relating to “Chestnut Field Well 22/2A-15, Block 22/2A, Chestnut Field”.
6 

(1) The Offshore Installations (Safety Zones) (No. 2) Order 2022, is amended as follows.
(2) In the Schedule (installations), in Part 1, omit the entry relating to “Kingfisher BP1.1 Wellhead, Kingfisher, Block 16/8a”.
Signed by the authority of the Secretary of State for Work and Pensions
Stephen Timms
Minister of State
Department for Work and Pensions
8th December 2025
Schedule
Article 2


(1) Name or other designation (2) Latitude (3) Longitude
Abbey Wellhead Protection Structure, Abbey Field, Block 47/03i 53° 56.08’N 00° 31.35’E
Galahad Installation, Galahad Field, Block 48/12a 53° 32.75’N 01° 21.54’E