1 
This Order may be cited as the A122 (Lower Thames Crossing) Development Consent (Amendment) (No. 2) Order 2025 and comes into force on 5th November 2025.
2 

(1) The A122 (Lower Thames Crossing) Development Consent Order 2025 is amended as follows.
(2) In article 65 (financial arrangements for the Kent Downs National Landscape)—
(a) for paragraph (2), substitute—“
(2) The agreement referred to in paragraph (1) is to be made prior to the commencement of any part of the authorised development located south of the River Thames.”; and
(b) after paragraph (7), insert—“
(8) In this article “commencement” has the same meaning as in paragraph 1(1) (interpretation) of Part 1 of Schedule 2 (requirements).”.
Signed by authority of the Secretary of State for Transport
Kayla Marks
Head of the Transport and Works Act Orders Unit
Department for Transport
4th November 2025