1 
This Order may be cited as the M5 Junction 10 Development Consent (Correction) Order 2025 and comes into force on 3rd November 2025.
2 
The 2025 Order is corrected as set out in the table in the Schedule, where—
(a) column 1 sets out where the correction is to be made;
(b) column 2 sets out how the correction is to be made; and
(c) column 3 sets out the text to be substituted, inserted or omitted.
Signed by authority of the Secretary of State for Transport
Samantha Collins-Hill
Deputy Director, Transport Planning
Department for Transport
29th October 2025
Schedule
Article 2

(1)Where the correction is to be made (2)How the correction is to be made (3)Text to be substituted, inserted or omitted
Part 3, Article 11(5) For “42 days” substitute “28 days”
Schedule 2, paragraph 11(3)(a) For “relevant planning authority” substitute “Secretary of State“
Schedule 10 In relation to the “environmental statement - appendix 1.1: glossary” for “0” substitute “1”
Schedule 10 In relation to the “environmental statement - appendix 1.2: scoping opinion responses” for “0” substitute “1”