1 
This Order may be cited as the Hornsea Four Offshore Wind Farm (Amendment) Order 2024 and comes into force on 18th July 2024.
2 
The Hornsea Four Offshore Wind Farm Order 2023 (“the 2023 Order”) is amended in accordance with this Order.
3 
In Part 2 of Schedule 16 to the 2023 Order—
(a) in paragraph 3(d) for “four full kittiwake breeding seasons” substitute “two full kittiwake breeding seasons”; and
(b) in paragraph 4, for “four full breeding seasons” substitute “two full breeding seasons”.
Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Energy Infrastructure Planning Delivery
Head of 
Department for Energy Security and Net Zero
17th July 2024