1 

(1) This Order may be cited as the Offshore Installations (Safety Zones) (No. 2) Order 2024.
(2) This Order comes into force 21 days after the day on which it is made (“the general coming into force date”), except for article 2(1), which comes into force as provided in article 2(2).
2 

(1) A safety zone is established around the installation specified in column 1 of the table in the Schedule (being an installation to be stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of 500 metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the table in the Schedule.
(2) Paragraph (1) comes into force, as respects the installation—
(a) on the general coming into force date, where the installation arrives at its station before that date; and
(b) when the installation arrives at its station, in any other case.
3 

(1) The Offshore Installations (Safety Zones) Order 1997 is amended as follows.
(2) In Schedule 1 (safety zones), omit the entry relating to “Curlew B—Wellhead”.
4 

(1) The Offshore Installations (Safety Zones) (No. 3) Order 2000 is amended as follows.
(2) In the Schedule (safety zones), omit the entry relating to “Wellheads and manifold, Block 211, Don Field”.
5 

(1) The Offshore Installations (Safety Zones) (No. 3) Order 2011 is amended as follows.
(2) In the Schedule (safety zone), omit the entry relating to “Athena Manifold Centre, Block 14/18b, Athena Field”.
6 

(1) The Offshore Installations (Safety Zones) (No. 2) Order 2016 is amended as follows.
(2) In the Schedule (installations), in Part 1, omit the entry relating to “Athena Riser Base, Block 14/18b, Athena Field”.
7 

(1) The Offshore Installations (Safety Zones) Order 2023 is amended as follows.
(2) In the Schedule (installations), omit the entry relating to “Schooner, Schooner, Block 44/26a”.
Signed by the authority of the Secretary of State for Work and Pensions
Stephen Timms
Minister of State
Department for Work and Pensions
3rd December 2024
Schedule
Article 2


(1) Name or other designation (2) Latitude (3) Longitude
Victory Development, Victory Field, Block 207/1a 60° 58.10’N 01° 54.61’W