1 
This Order may be cited as the Sunnica Energy Farm (Correction) Order 2024 and comes into force on 13thNovember 2024.
2 
The Sunnica Energy Farm Order 2024 is corrected as set out in the table in the Schedule to the Order, in which—
(a) column 1 sets out where the correction is to be made;
(b) column 2 sets out how the correction is to be made; and
(c) column 3 sets out the text which is to be substituted, inserted or omitted.
Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning Delivery
Department for Energy Security and Net Zero
12th November 2024
SCHEDULE
Article 2


Column (1)Where the correction is made Column (2)How the correction is made Column (3)Text substituted, inserted or omitted
Article 35(2)(d) After “breach”, omit “of”
Schedule 2, Requirement 6(1)(k) For “/” substitute “or”
Schedule 2, Requirement 6(1)(k) For “Construction and Traffic Management Plan,” substitute “framework construction traffic management plan and travel plan,”
Schedule 8, row: 1-02 Omit Row 1-02
Schedule 8, row: 1-03 Omit Row 1-03
Schedule 8, row: 5-11 Omit Row 5-11
Schedule 8, row: 16-14, column (2) Omit “and access rights”
Schedule 8, row: 16-15, column (2) After “Cable rights”, insert “and access rights”
Schedule 10, row: land and Crown land plans, column (3) For “7”, substitute “6”
Schedule 10, row: land and Crown land plans, column (4) For “30/08/2023”, substitute “30/01/2023”
Schedule 12, paragraph 14(4) For “39”, substitute “38”
Schedule 12, paragraph 99(2) For “(cable works beneath the width of the highway)”, substitute “(streets subject to street works)”