1 
This Order may be cited as the Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) (Correction) Order 2023 and comes into force on 20th April 2023.
2 
The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 is corrected as set out in the table in the Schedule to this Order, where—
(a) column 1 sets out where the correction is to be made;
(b) column 2 sets out how the correction is to be made; and
(c) column 3 sets out the text to be substituted, inserted or omitted.
Signed by authority of the Secretary of State for Energy, Security and Net Zero
David Wagstaff
Deputy Director Energy Infrastructure Planning
Department for Energy, Security and Net Zero
18th April 2023
SCHEDULE
Article 2


Provision How correction is to be made Text to be substituted, inserted or omitted
Article 2 (interpretation) “carbon capture and compression plant” After “No 7” add “as set out”
Article 2 (interpretation) “carbon capture and compression plant” After “Schedule 1” add “and as”
Article 21(3) Substitute “4A and 4B” for “4A or 4B”
Article 21(3) After “(1) are” add “respectively”
Schedule 9 (procedure for discharge of requirements) paragraph 4(2)(2) sub paragraph (ii) Substitute “pursuan” for “pursuant”