1 
This Order may be cited as the Immingham Open Cycle Gas Turbine (Amendment) Order 2023 and comes into force on 1stFebruary 2023.
2 
The Immingham Open Cycle Gas Turbine Order 2020 is amended in accordance with this Order.
3 
In article 2 (interpretation) of Part 1 (preliminary) in the definition of “commissioning”, after the words “the undertaker’s operational and safety requirements”, insert “and the words “commission” and “commissioned” and cognate expressions are to be construed accordingly;”.
4 
In Schedule 1 (authorised development), in the description of Work No. 1—
(a) at the end of sub-paragraph (u) delete “and”; and
(b) at the end of sub-paragraph (v) insert—“and
(w) synchronous condenser.”.
5 
In Schedule 2 (requirements), in paragraph 11 sub-paragraph (3) after the words “No part of the authorised development may commence” insert “save for the permitted preliminary works”.
Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy
David Wagstaff
Deputy Director – Energy Development and Resilience
Department for Business, Energy and Industrial Strategy
31st January 2023