Article 1 
The overcompensation for the period from 1 September 2005 to 30 June 2011 amounting to PLN 894 956 888,88, granted by Poland to Autostrada Wielkopolska S. A. on the basis of the Amendment Act, constitutes State aid within the meaning of Article 107(1) of the Treaty.
Article 2 
The State aid referred to in Article 1 is unlawful as it was granted in breach of the notification and standstill obligations stemming from Article 108(3) of the Treaty.
Article 3 
The State aid referred to in Article 1 is incompatible with the internal market.
Article 4 

1. Poland shall recover the aid referred to in Article 1 from the beneficiary.
2. The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiary until their actual recovery.
3. The interest shall be calculated on a compound basis in accordance with Chapter V of Commission Regulation (EC) No 794/2004 as last amended by Regulation (EC) No 271/2008.
Article 5 

1. Recovery of the aid referred to in Article 1 shall be immediate and effective.
2. Poland shall ensure that this decision is implemented within four months following the date of notification of this Decision.
Article 6 

1. Within two months following notification of this Decision, Poland shall submit the following information to the Commission:
(a) the total amount (principal and recovery interests) to be recovered from the beneficiary;
(b) a detailed description of the measures already taken and planned to comply with this Decision;
(c) documents demonstrating that the beneficiary has been ordered to repay the aid.
2. Poland shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 1 has been completed. It shall immediately submit, on simple request by the Commission, information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiary
Article 7 
This Decision is addressed to the Republic of Poland.
Done at Brussels, 25 August 2017.
For the Commission
Margrethe VESTAGER
Member of the Commission
ANNEX

Compensation period Overcompensation (gross) in PLN  Compensation period Overcompensation (gross) in PLN
September 2005 […]  August 2008 […]
October 2005 […]  September 2008 […]
November 2005 […]  October 2008 […]
December 2005 […]  November 2008 […]
January 2006 […]  December 2008 […]
February 2006 […]  January 2009 […]
March 2006 […]  February 2009 […]
April 2006 […]  March 2009 […]
May 2006 […]  April 2009 […]
June 2006 […]  May 2009 […]
July 2006 […]  June 2009 […]
August 2006 […]  July 2009 […]
September 2006 […]  August 2009 […]
October 2006 […]  September 2009 […]
November 2006 […]  October 2009 […]
December 2006 […]  November 2009 […]
January 2007 […]  December 2009 […]
February 2007 […]  January 2010 […]
March 2007 […]  February 2010 […]
April 2007 […]  March 2010 […]
May 2007 […]  April 2010 […]
June 2007 […]  May 2010 […]
July 2007 […]  June 2010 […]
August 2007 […]  July 2010 […]
September 2007 […]  August 2010 […]
October 2007 […]  September 2010 […]
November 2007 […]  October 2010 […]
December 2007 […]  November 2010 […]
January 2008 […]  December 2010 […]
February 2008 […]  January 2011 […]
March 2008 […]  February 2011 […]
April 2008 […]  March 2011 […]
May 2008 […]  April 2011 […]
June 2008 […]  May 2011 […]
July 2008 […]  June 2011 […]
   Total 894 956 888,88