Article 1 
The State aid amounting to EUR 2 406 415, unlawfully granted by Germany to HoKaWe Eberswalde GmbH in breach of Article 108(3) of the Treaty on the Functioning of the European Union, is incompatible with the internal market.
Article 2 

1. Germany shall recover the aid referred to in Article 1 from the beneficiary.
2. The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiary until their actual recovery.
3. The interest shall be calculated on a compound basis in accordance with Chapter V of Commission Regulation (EC) No 794/2004 and Commission Regulation (EC) No 271/2008 amending Regulation (EC) No 794/2004.
Article 3 

1. Recovery of the aid referred to in Article 1 shall be immediate and effective.
2. Germany shall ensure that this Decision is implemented within four months following the date of notification of this Decision.
Article 4 

1. Within two months following notification of this Decision, Germany shall submit the following information to the Commission:
(a) the total amount (principal and recovery interest) to be recovered from the beneficiary;
(b) a detailed description of the measures already taken and planned to comply with this Decision;
(c) documents demonstrating that the beneficiary has been ordered to repay the aid.
2. Germany shall keep the C⊙mmission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 1 has been completed. It shall immediately submit, on simple request by the Commission, information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiary
Article 5 
This Decision is addressed to the Federal Republic of Germany.
Done at Brussels, 6 November 2013.
For the Commission
Joaquín ALMUNIA
Vice-President