1 

(1) This Order may be cited as the Offshore Installations (Safety Zones) Order 2013.
(2) This Order comes into force on 6th August 2013 except for article 2(2) which comes into force as provided in article 2(3).
2 

(1) A safety zone is established around each installation specified in column 1 of Part 1 of the Schedule (being an installation stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of Part 1 of the Schedule.
(2) A safety zone is established around each installation specified in column 1 of Part 2 of the Schedule (being an installation to be stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of Part 2 of the Schedule.
(3) Paragraph (2) comes into force, as respects each installation specified in column 1 of Part 2 of the Schedule, when the installation arrives at its station.
3 
In the Offshore Installations (Safety Zones) (No. 3) Order 2004, in the Schedule, omit the entry for Arthur Production Well 1 and Subsea Manifold including its co-ordinates.
Signed by authority of the Secretary of State for Work and Pensions
Mark Hoban
Minister of State
Department for Work and Pensions
15th July 2013
SCHEDULE
Article 2
PART 1

(1)Name or other designation of the offshore installation (2)Latitude (3)Longitude
Arthur Production Well 1 and Subsea ManifoldBlock 53/02, Thames and Welland Field 52°54.726’ North 02°14.847’ East
Carrack East Drill Site Block 49/15a, Carrack Field 53°34.53’ North 02°52.86’ East
Carrack West Drill SiteBlock 49/14b, Carrack Field 53°35.84’ North 02°41.85’ East
. . .

  
Production Well P1Block 211/23d, Causeway Field 61°16.49’ North 01°25.83’ East
Production Well P2Block 211/22a, Fionn Field 61°14.44’ North 01°22.06’ East
Schiehallion Block 204/20, Schiehallion/Loyal Field 60°21.38’ North 04°04.07’ West
Water Injection Well WI Block 211/23d, Causeway Field 61°15.75’ North 01°25.54’ East
PART 2

(1)Name or other designation of the offshore installation (2)Latitude (3)Longitude
Galia Production Drill CentreBlock 30/24b, Galia Field 56°11.147’ North 02°41.325’ East
Juliet Subsea ManifoldBlock 47/14b, Juliet Field 53°33.19’ North 00°45.25’ East
Kew WellheadBlock 49/04c, Chiswick Field 53°57.30’ North 02°47.07’ East
Solan Production Well P1Block 205/26a, Solan Field 60°03.84’ North 03°58.53’ West
Solan Production Well P2Block 205/26a, Solan Field 60°03.76’ North 03°58.68’ West