1 
This Order may be cited as the Offshore Installations (Safety Zones) Order 2011 and comes into force on 28th March 2011.
2 
A safety zone is established around each installation specified in column 1 of the Schedule (being installations stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the Schedule.
Signed by authority of the Secretary of State for Work and Pensions
Chris Grayling,
Minister of State
Department for Work and Pensions
2nd March 2011
SCHEDULE
Article 2


(1)Name or other designation of the offshore installation (2)Latitude North (3)Longitude
Kinnoull TowheadBlock 16/23, Andrew Field 58°14.23’ 01°34.21’ East
Clair RidgeBlock 206/8, Clair Field 60°44.18’ 02°29.65’ West
Falcon Well P1Block 210/25, Falcon Field 61°19.80’ 00°59.36’ East