1 
This Order may be cited as the Offshore Installations (Safety Zones) (No.3) Order 2011 and comes into force on 1st October 2011.
2 
A safety zone is established around each installation specified in column 1 of the Schedule (being installations stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the Schedule.
Signed by authority of the Secretary of State for Work and Pensions.
C Grayling
Minister of State,
Department for Works and Pensions
6th September 2011
SCHEDULE
Article 2


(1)Name or other designation of the offshore installation (2)Latitude (3)Longitude
. . . . . . . . .
Laggan Manifold,Block 206/1A,Laggan Tormore Field 60°56.67’North 2°53.62’West
Tormore Manifold,Block 205/5A,Laggan Tormore Field 60°52.28’North 3°8.23’West