1 

(1) This Order may be cited as the Renewables Obligation (Scotland) Amendment Order 2018 and comes into force on 20th November 2018.
(2) In this Order “the 2009 Order” means the Renewables Obligation (Scotland) Order 2009.
2 
The 2009 Order is amended in accordance with articles 3 and 4.
3 
In article 2 (interpretation), in the definition of “excluded capacity”, after paragraph (a) insert—“
(ab) in relation to a large hydro generating station, generating capacity which in the Authority’s view—
(i) formed part of the station from a date no earlier than 20th November 2018; and
(ii) does not form part of the capacity of the station as accredited.”.
4 
In article 17 (excluded generating stations), omit paragraph (4).
PAUL WHEELHOUSE
Authorised to sign by the Scottish Ministers
St Andrew’s House,
Edinburgh
13th November 2018