Article 1 

1. This Regulation sets out the modalities for the calculation of the costs directly incurred as a result of operating the train service for the purpose of setting the charges for the minimum access package and access to infrastructure connecting service facilities referred to in Article 31(3) of Directive 2012/34/EU.
2. This Regulation shall apply without prejudice to the provisions regarding the financing of infrastructure or the equilibrium of income and expenditure of the infrastructure manager set out in Article 8 of Directive 2012/34/EU.
Article 2 
For the purposes of this Regulation, the following definitions shall apply:

((1)) ‘direct cost’ means the cost which is directly incurred as a result of operating the train service;
((2)) ‘direct unit cost’ means the direct cost per train kilometre, vehicle kilometre, gross tonne kilometre of a train, or a combination of those;
((3)) ‘cost centre’ means a business unit within the infrastructure manager's accounting system to which costs are allocated for the sake of apportioning those costs directly or indirectly to a marketable service.
Article 3 

1. Direct costs on a network-wide basis shall be calculated as the difference between, on the one hand, the costs for providing the services of the minimum access package and for the access to the infrastructure connecting service facilities and, on the other hand, the non-eligible costs referred to in Article 4.
2. The Member State may decide that the infrastructure manager applies the costs of efficient service provision for the purposes of calculation of direct costs on a network-wide basis referred to in paragraph 1.
3. Asset values used for the purpose of calculating direct costs on a network-wide basis shall be based on historic values or, where such values are not available or where current values are lower, on current values. Historic values of the assets shall be based on the amounts paid and documented by the infrastructure manager at the time of acquisition of these assets. In case of a debt relief, whereby all of part of the infrastructure manager's debts have been assumed by another entity, the infrastructure manager shall attribute a relevant part of the debt relief to reduce its asset values and the corresponding direct costs on a network-wide basis. By derogation from the first sentence, the infrastructure manager may apply values including estimated values or current values or replacement values if they can be transparently, robustly and objectively measured and duly justified to the regulatory body.
4. Without prejudice to Article 4 and if the infrastructure manager can transparently, robustly, and objectively measure and demonstrate on the basis of, inter alia, best international practice that costs are directly incurred by the operation of the train service, the infrastructure manager may include in the calculation of its direct costs on a network-wide basis in particular the following costs:
(a) costs of staff needed for keeping open a particular stretch of line if an applicant requests to run a specific train service scheduled outside the regular opening hours of this line;
(b) the part of the costs of points infrastructure, including switches and crossings, that is exposed to wear and tear by the train service;
(c) the part of the costs of renewing and maintaining the overhead wire or the electrified third rail or both and the supporting overhead line equipment directly incurred as a result of operating the train service;
(d) the costs of staff needed for preparing the allocation of train paths and the timetable to the extent that they are directly incurred as a result of operating the train service.
5. Costs used for calculation under this Article shall be based on payments effected or forecast by the infrastructure manager. Costs calculated under this Article shall be measured or forecast consistently on the basis of data from the same time period.
Article 4 

1. The infrastructure manager shall not include in the calculation of direct costs on a network-wide basis in particular the following costs:
(a) fixed costs relating to the provision of a stretch of line which the infrastructure manager must bear even in the absence of train movements;
(b) costs that do not relate to payments made by the infrastructure manager. Costs or cost centres that are not directly linked to the provision of the minimum access package or to access to infrastructure connecting service facilities;
(c) costs of acquisition, selling, dismantling, decontamination, recultivation or renting of land or other fixed assets;
(d) network-wide overhead costs, including overhead salaries and pensions;
(e) financing costs;
(f) costs related to technological progress or obsolescence;
(g) costs of intangible assets;
(h) costs of track-side sensors, track-side communication equipment and signalling equipment if not directly incurred by operation of the train service;
(i) costs of information, non-track side located communication equipment or telecommunication equipment;
(j) costs related to individual incidences of force majeure, accidents and service disruptions without prejudice to Article 35 of Directive 2012/34/EU;
(k) costs of electric supply equipment for traction current if not directly incurred by operation of the train service. Direct costs of operation of the train services that do not use electric supply equipment shall not include costs of using the electric supply equipment;
(l) costs related to the provision of information mentioned under item 1(f) of Annex II to Directive 2012/34/EU, unless incurred by operation of the train service;
(m) administrative costs incurred by schemes of differentiated charges referred to in Articles 31(5) and 32(4) of Directive 2012/34/EU;
(n) depreciation which is not determined on the basis of real wear and tear of infrastructure due to the train service operation;
(o) the part of the costs of maintenance and renewal of civil infrastructure that is not directly incurred by operation of the train service.
2. If the infrastructure manager received funding to finance specific infrastructure investments, which it is not obliged to repay and where such investments are taken into account in the calculation of direct costs, the costs of such investments shall not increase the level of charges without prejudice to Article 32 of Directive 2012/34/EU.
3. Costs excluded from calculation by virtue of this Article shall be measured or forecast on the basis of the time period referred to in Article 3(5).
Article 5 

1. The infrastructure manager shall calculate average direct unit costs for the entire network by dividing the direct costs on a network-wide basis by the total number of vehicle kilometres, train kilometres or gross tonne kilometres forecasted for or actually operated.Alternatively, if the infrastructure manager demonstrates to the regulatory body referred to in Article 55 of Directive 2012/34/EU that the values or parameters mentioned in paragraph 2 are significantly different for different parts of its network, and after splitting its network into such parts, the infrastructure manager shall calculate average direct unit costs for the parts of its network by dividing the direct costs for these parts by the total number of vehicle kilometres, train kilometres or gross tonne kilometres forecast for or actually operated. The period of the forecast may cover several years.In order to calculate the average direct unit costs, the infrastructure manager may use a combination of vehicle kilometres, train kilometres or gross tonne kilometres provided this method of calculation does not alter the direct causation link with the operation of the train service. Without prejudice to Article 3(3), the infrastructure manager may apply outturn or forecast costs.
2. Member States may allow the infrastructure manager to modulate the average direct unit costs to take into account the different levels of wear and tear caused to the infrastructure according to one or more of the following parameters:
(a) train length and/or number of vehicles in the train;
(b) train mass;
(c) type of vehicle, in particular its unsprung mass;
(d) train speed;
(e) traction power of the motorised unit;
(f) axle weight and/or axle numbers;
(g) recorded number of wheel flats or the effective use of equipment to protect against wheel slips;
(h) longitudinal stiffness of vehicles and horizontal forces impacting on the track;
(i) consumed and measured electric power or the dynamics of pantographs or contact shoes as a parameter to charge for the wear and tear of the overhead wire or the electric rail;
(j) track parameters, in particular radii;
(k) any other cost related parameters where the infrastructure manager can demonstrate to the regulatory body that values for each such parameter, including variation to each such parameter where relevant, are objectively measured and recorded.
3. A modulation of the direct unit costs shall not result in an increase of the direct costs on a network-wide basis as referred to in Article 3(1).
4. Additional costs incurred by the diversion, scheduled or otherwise, of trains at the instigation of the infrastructure manager shall not be included in the direct costs incurred by the operation of these train services. The first sentence shall not apply if the railway undertaking is reimbursed for those additional costs by the infrastructure manager or the diversion resulted from a coordination procedure in accordance with Article 46 of Directive 2012/34/EU.
5. The total number of vehicle kilometres, train kilometres, gross tonne kilometres or a combination of those used for the purposes of the calculations made under this Article shall be measured or forecast on the basis of the reference period referred to in Article 3(5).
Article 6 
By derogation to Article 3(1) and the first sentence of Article 5(1), the infrastructure manager may calculate direct unit costs by means of robustly evidenced econometric or engineering cost modelling, provided it can demonstrate to the regulatory body that the direct unit costs include only direct costs incurred by the operation of the train service and, in particular, do not include any of the costs referred to in Article 4. The regulatory body may request the infrastructure manager to calculate for comparison direct unit costs in accordance with Article 3(1) and Article 5(1) or by means of cost modelling in accordance with the first sentence.
Article 7 

1. If direct costs on a network-wide basis referred to in Article 3(1) or direct costs calculated on the basis of modelling referred to in Article 6 multiplied by the number of train kilometres, vehicle kilometres and/or gross tonne kilometre, operated in the reference period are equivalent to either less than 15 % of the full costs of maintenance and renewal or less than the sum of 10 % of maintenance costs and 20 % of renewal costs, the regulatory body may carry out the control referred to in Article 56(2) of Directive 2012/34/EU over the calculation of direct costs on a network-wide basis in a simplified manner. Member States may decide to increase the percentages mentioned in this paragraph to not more than twice the indicated values.
2. The regulatory body may accept the calculation of the average direct unit costs referred to in Article 5(1) and the modulated average direct unit costs referred to in Article 5(2) and/or cost modelling referred to in article 6 subject to the simplified control referred to in paragraph 1 of this Article if the average direct costs per train kilometre of a 1 000 tonne train amounts to not more than EUR 2 (at 2005 prices and exchange rates, using an appropriate price index).
3. Simplified controls as referred to in paragraphs 1 and 2 shall be applied independently from one another. Simplified controls shall be without prejudice to Articles 31 or 56 of Directive 2012/34/EU.
4. The regulatory body shall determine the details of the simplified control.
Article 8 
The infrastructure manager shall regularly update the method of calculation of its direct costs taking into account, inter alia, the best international practice.
Article 9 
The infrastructure manager shall submit its method of calculation of direct costs and, if applicable, a phasing-in plan to the regulatory body no later than 3 July 2017.
Article 10 
This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.
It shall apply from 1 August 2015.
This Regulation shall be binding in its entirety and directly applicable in all Member States.Done at Brussels, 12 June 2015.
For the Commission
The President
Jean-Claude JUNCKER