Article 1 

1. This Regulation sets out the modalities to be followed by the infrastructure manager for the application of the charging for the cost of noise effects caused by the freight rolling stock.It shall apply when a Member State, within the charging framework as provided for in Article 29(1) of Directive 2012/34/EU, has decided to introduce modification of infrastructure charges in accordance with Article 31(5), first subparagraph of that Directive.
2. This Regulation shall not apply to wagons which fulfil one of the following conditions:
(a) wagons that hold a derogation from TSI Noise under Article 9 of Directive 2008/57/EC of the European Parliament and of the Council;
(b) wagons for which there are no available TSI Wagon compliant composite brake blocks which can be directly fitted in the wagon without further modification of the braking system or dedicated tests;
(c) wagons coming from third countries and running on 1 520 or 1 524 mm railway gauge network and which are granted a specific case in TSI Noise or excluded from its scope.
3. The bonus and the malus resulting from the differentiation of the track access charges shall ensure non-discriminatory and transparent access to infrastructure.
4. The differentiation of the track access charges according to this Regulation shall be without prejudice to the application of State aid rules.
Article 2 
For the purpose of this Regulation, the following definitions shall apply:

((1)) ‘Scheme’ means provisions establishing noise-differentiated track access charges to be adopted and applied by infrastructure managers;
((2)) ‘Retrofitted wagons’ means existing wagons retrofitted with composite brake blocks in accordance with the requirements set out in TSI Noise;
((3)) ‘Silent wagons’ means new or existing wagons respecting relevant noise limit values set out in TSI Noise;
((4)) ‘Noisy wagons’ means wagons not respecting relevant noise limit values set out in TSI Noise;
((5)) ‘Noisy train’ means a train composed of more than 10 % of noisy wagons;
((6)) ‘Silent train’ means a train which is composed of at least 90 % of silent wagons;
((7)) ‘Very quiet wagons and locomotives’ means wagons and locomotives with noise emissions at least 3 dB below the relevant values set out in TSI Noise;
((8)) ‘Bonus for retrofitted wagons’ means a mandatory discount from the infrastructure access charges for railway undertakings using retrofitted wagons;
((9)) ‘Train bonus’ means an optional discount for railway undertakings for each ‘silent train’;
((10)) ‘Bonus for very quiet wagons or locomotives’ means an optional discount for railway undertakings for each very quiet wagon and locomotive;
((11)) ‘Malus’ means an optional surcharge to the infrastructure access charges to be paid by railway undertakings for each noisy train.
Article 3 

1. On the basis of the modalities set out in this Regulation, the infrastructure manager shall adopt a scheme which differentiates the infrastructure charges depending on the level of noise produced and which applies to all railway undertakings concerned. The application of this scheme shall not result in the undue distortion of competition between railway undertakings or negatively affect the overall competitiveness of the rail freight sector.
2. The scheme shall apply until 31 December 2021.
Article 4 

1. Infrastructure managers shall introduce a bonus for railway undertakings using retrofitted wagons. The level of bonus shall be the same on the entire network of the infrastructure manager and it shall be applicable to each retrofitted wagon.
2. The basis for calculation of the level of bonus shall be the number of axles of a wagon and amount of kilometres run in a period determined by the infrastructure manager.
3. The minimum level of a bonus shall be set at EUR 0,0035 per axle-km.
4. When setting the level of the bonus, the infrastructure manager may take into account the inflation, mileage run by wagons and operating costs linked with the use of retrofitted wagons.
5. The level of bonus calculated in accordance with paragraph 3 and, where relevant, paragraph 4 shall be set for at least 1 year.
6. Infrastructure managers may decide to cancel or reduce the level of bonus by the value of retrofitting costs for those wagons that had already received bonus payments which allow them to reimburse the retrofitting costs.
Article 5 

1. Infrastructure managers may introduce a bonus for railway undertakings running silent trains.
2. Train bonus shall be applicable to each silent train.
3. The amount of the bonus for silent train shall be maximum 50 % of the total value of bonuses applicable to retrofitted wagons composing that train and calculated in accordance with Article 4.
4. The bonus for silent train shall be cumulative with the bonuses referred to in Articles 4 and 6.
Article 6 

1. Infrastructure managers may introduce a bonus for railway undertakings running very quiet wagons and locomotives.
2. Bonus referred to in paragraph 1 shall be applicable to each very quiet wagon and locomotive.
3. The amount of the bonus for each very quiet wagon and locomotive shall proportionally correspond to the reduction of noise levels below these limit values and shall be maximum 50 % of the value of bonus applicable to the retrofitted wagon as calculated in accordance with Article 4.
4. The bonus for very quiet wagons and locomotives shall be cumulative with the bonuses referred to in Articles 4 and 5.
Article 7 

1. Infrastructure managers may introduce a malus for railway undertakings running noisy trains.
2. Malus shall be applicable to each noisy train.
3. The total sum of malus paid over the duration of the scheme shall not be higher than the sum of bonuses referred to in Articles 4, 5 and 6.
4. Infrastructure managers shall be allowed not to apply paragraph 3 if similar charging of cost of noise is applied to road freight transport in accordance with Union law in the Member State concerned.
5. By derogation from Article 3 Member States may decide to continue to apply or introduce a malus after the end of the duration of the scheme under condition that a similar measure is applied to road freight transport sector in accordance with Union law.
6. When deciding to introduce the malus and setting its level, the infrastructure manager may, as appropriate and after consulting the relevant stakeholders, take into account the sensitivity of the area affected by rail freight traffic, in particular the size of population affected and its exposure to rail noise along the railway line.
Article 8 

1. Infrastructure managers shall be responsible for managing the scheme, including keeping the accounts for financial flows with railway undertakings. They shall make available the data concerning these financial flows upon request of the competent national authorities during the period of application of the scheme and in the following 10 years after the expiry of the scheme.
2. Infrastructure manager shall use existing registers and other available tools in order to gather evidence demonstrating the status of the wagons or locomotives (accordingly retrofitted, silent or noisy, very quiet).
3. If the data referred to in paragraph 2 cannot be gathered from registers or tools, the infrastructure manager shall request the railway undertakings to demonstrate the status of the wagons and locomotives they intend to use.In case of retrofitted wagon, the railway undertaking shall deliver relevant technical or financial evidence that the retrofitting took place.In case of silent wagons, the railway undertaking shall deliver an authorisation to place in service or any equivalent evidence.In case of very quiet wagons and locomotives, the railway undertaking shall deliver evidence proving the lower level of noise, including, if appropriate, details of additional noise reduction modifications undertaken.
4. Administrative measures developed at national level for the management of the existing schemes may continue to apply as long as they comply with this Regulation.
5. Administrative costs of the scheme shall not be taken into account in the determination of the level of bonus and malus.
6. Infrastructure managers of Member States applying the scheme shall cooperate, in particular regarding the simplification and harmonisation of administrative procedures for the application of the charging for the cost of noise effects caused by the freight rolling stock as provided for by this Regulation, including on the format of the evidence referred to in paragraph 3.
Article 9 

1. The schemes shall be notified to the Commission before they become applicable.
2. By 1 May 2016, and by 1 May of each following year the Member States shall report to the Commission for the previous calendar year at least the following data:
(a) number of wagons that were subject to bonus referred to in Article 4;
(b) where applicable, number of wagons and locomotives subject to bonus referred to in Article 6;
(c) where applicable, number of trains subject to bonus referred to in Article 5;
(d) where applicable, number of trains that were subject to malus;
(e) mileage run by retrofitted wagons in the Member State concerned;
(f) estimated mileage run by silent and noisy trains in the Member State concerned.
3. Upon request of the Commission additional data shall be provided where available. This data may include:
(a) total amount of bonuses granted for retrofitted wagons, silent trains and very quiet wagons and locomotives;
(b) total amount of maluses collected;
(c) average amount of bonus and malus per axle-km.
Article 10 

1. By 31 December 2018, the Commission shall evaluate the implementation of the schemes, in particular regarding the progress of retrofitting of wagons and the balance between bonus deducted and malus already paid. In addition, the Commission shall evaluate the impact of the schemes put in place according to this Regulation on the overall competitiveness of the freight railway sector and the passing on of the incentives induced through the scheme from railway undertakings to wagon keepers.
2. Taking into account the results of the evaluation, the Commission may if necessary, amend this Regulation in particular in relation to the minimum level of bonus.
Article 11 

1. Existing schemes at the date of the entry into force of this Regulation, including contracts based on such schemes, may continue to apply until 10 December 2016 at the latest. The scheme provided for by this Regulation may only be applied after the existing schemes have been terminated. Termination of existing schemes shall not be required if the infrastructure manager has made the existing scheme and contracts based on it compliant with this Regulation by 11 December 2016.
2. Infrastructure managers from Member States that had in place schemes referred to in paragraph 1 may decide not to apply Article 3(2) as long as the total duration of their schemes is at least of 6 years.
Article 12 
This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.
It shall apply from 16 June 2015.
This Regulation shall be binding in its entirety and directly applicable in the Member States.Done at Brussels, 13 March 2015.
For the Commission
The President
Jean-Claude JUNCKER