The Commission establishes for the development of harmonised electricity rules this annual priority list for 2015:

— network connection rules:
— rules on requirements for grid connection applicable to generators (Commission adoption phase),
— demand connection (Commission adoption phase),
— rules on high-voltage direct current transmission system connection (finalise network code and start Commission adoption phase),
— system operation rules:
— rules on load-frequency control and reserves (Commission adoption phase),
— rules on emergency requirements & procedures (finalise network code and start Commission adoption phase),
— rules on operational security (Commission adoption phase),
— rules on operational planning and scheduling (Commission adoption phase),
— rules on capacity allocation and congestion management for day-ahead and intraday markets, including capacity calculation (Commission adoption phase),
— balancing rules including network-related reserve power (finalise network code and start Commission adoption phase),
— rules for longer term (forward) capacity allocation (Commission adoption phase),
— rules regarding harmonised transmission tariff structures (scoping by ACER to prepare framework guideline).
Article 2 
The Commission establishes for the development of harmonised gas rules this annual priority list for 2015:

— interoperability and data exchange rules (Commission adoption phase),
— rules regarding harmonised transmission tariff structures (finalise network code and start Commission adoption phase),
— rules regarding an EU-wide market-based approach on the allocation of ‘new build’ gas transmission capacity (finalise amendment proposal of capacity allocation mechanisms network code and start Commission adoption phase).
Article 3 
This Decision shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.
Done at Brussels, 13 October 2014.
For the Commission
The President