1 
This Order may be cited as the Edinburgh Tram (Line Two) Act 2006 (Extension of Time for Land Acquisition) Order 2011 and comes into force on 1st April 2011.
2 
The period referred to in section 40(1) of the Edinburgh Tram (Line Two) Act 2006 is extended until 26th April 2021.
KEITH BROWN
Authorised to sign by the Scottish Ministers
St Andrew’s House,
Edinburgh
17th February 2011