(1) These Regulations may be cited as the Channel Tunnel Rail Link (Assessment of Environmental Effects) Regulations 1999 and shall come into force on 17th February 1999.
(2) In these Regulations–
 “the 1988 Regulations” means the Town and Country Planning (Assessment of Environmental Effects) Regulations 1988;
 “the 1994 Environmental Statement” means the document called “The Environmental Statement for the Channel Tunnel Rail Link” deposited with the Bill for the 1996 Act pursuant to Standing Order 27A of the House of Commons upon the Bill’s introduction in the House of Commons on 23rd November 1994, including the supplements to that document deposited on 7th November 1995 and 5th December 1995;
 “the 1996 Act” means the Channel Tunnel Rail Link Act 1996;
 “exempt development” has the same meaning as in the 1988 Regulations;
 “relevant planning authority ” means the body by whom, assuming no directions have been given under paragraph 30 of Schedule 6 to the Channel Tunnel Rail Link Act 1996, a request for approval under Part II or III of that Schedule is determined; and
 “scheduled work” has the same meaning as in the 1996 Act.
2 
These Regulations apply to development consisting of the carrying out of any work authorised by the 1996 Act, other than–
(a) a development which consists of the carrying out of a scheduled work,
(b) a development which was commenced before the coming into force of these Regulations, or
(c) a development for which the plans, specifications, arrangements or schemes for the restitution of land required to be approved by the relevant planning authority under Part II or III of Schedule 6 to the 1996 Act were approved before the coming into force of these Regulations.
3 
The planning permission deemed to be granted by section 9(1) of the 1996 Act shall not apply to development to which these Regulations apply where–
(a) the 1994 Environmental Statement does not contain, in relation to that development, all the information specified in paragraph 2 of Schedule 3 to the 1988 Regulations;
(b) if the development were not authorised by the 1996 Act, it would not constitute exempt development; and
(c) the development is of a description mentioned in–
(i) Schedule 1 to the 1988 Regulations; or
(ii) Schedule 2 to the 1988 Regulations, and would be likely to have significant effects on the environment by virtue of factors such as its nature, size or location.
4 

(1) Regulations 2, 3, 4 and 6 of the Town and Country Planning (Environmental Assessment and Permitted Development) Regulations 1995, so far as not inconsistent with these Regulations, shall apply to development to which these Regulations apply, and shall have effect with the following modifications.
(2) 
(a) In regulation 2, for the words ““prospective developer”” to “would be determined;” there shall be substituted–“
 “nominated undertaker” has the same meaning as in the Channel Tunnel Rail Link Act 1996;
 “relevant development” means development to which the Channel Tunnel Rail Link (Assessment of Environmental Effects) Regulations 1999 apply;
 “relevant planning authority” has the same meaning as in the Channel Tunnel Rail Link (Assessment of Environmental Effects) Regulations 1999;”.
(b) In regulations 3 and 4, for “prospective developer” there shall be substituted “nominated undertaker”.
(c) In regulation 6(1)(e) and 6(2)(b), “or opinion” and “or 5” shall be omitted.
(d) In regulation 6(1)(f), “or opinion” shall be omitted.
(e) In the full out part of regulation 6(1), “opinion or” shall be omitted.
Signed by authority of the Secretary of State for the Environment, Transport and the Regions
Glenda Jackson
Parliamentary Under Secretary of State,
Department of the Environment, Transport and the Regions